The BBC reported on 12 November 2026 that Glen Rosa has set off from Greenock on builder’s sea trials, its first journey under its own power. The current timetable is for handover in February 2027, after the date was put back from the end of this year so the ship can be delivered with new redesigned propellers.

Source: BBC News (opens in a new tab)

View on map

The BBC reported on 12 November 2026 that the second of two long-delayed ferries built at the Ferguson Marine shipyard has set off for its builder’s sea trials. The 335ft (102m) long Glen Rosa set sail from Inchgreen quayside in Greenock, its first journey under its own power. It will undergo tests in the Firth of Clyde, with specialists checking its handling and propulsion systems.

Glen Rosa’s sister vessel, MV Glen Sannox, entered service with CalMac in January 2025 after years of delays. The current timetable is for Glen Rosa to be handed over in February 2027, after the expected date was put back from the end of this year to allow the ship to be delivered with new redesigned propellers. Ferguson Marine, which is based in Port Glasgow and owned by the Scottish government, said the new blades would address a vibration issue which emerged after its sister vessel Glen Sannox went into service last year. The dual-fuel ship is currently running on diesel, but its liquefied natural gas (LNG) systems are expected to be commissioned once the new propellers are fitted.

The sea trials will check the ferry’s propulsion, power generation, safety, automation and navigation systems, under real sailing conditions. Andrew Milligan, executive director of technical at Ferguson Marine, said: “Commencing sea trials is a pivotal moment for Glen Rosa and reflects the tremendous hard work and technical skill across our Port Glasgow shipyard.” He said: “These trials allow us to put the ship’s integrated systems through their paces at sea, validating months of dockside testing and outfitting.” He added: “Our team remains completely focused on producing quality work and rigorous testing, ensuring we deliver a reliable, robust vessel that will serve island communities for generations to come.”

Kevin Hobbs, chief executive of CMAL, which owns the ferries, said: “Builder’s sea trials are an important milestone, and we welcome the progress as we near the handover of MV Glen Rosa.”

The BBC describes builder’s sea trials as the first in a series of at-sea testing voyages of a ship, followed by owner’s acceptance trials and a final regulator approval process. Once delivered, CalMac will also want to conduct its own crew familiarisation and berthing trials before the ship begins carrying passengers.

  1. Flynn accepts a February 2027 handover for Glen Rosa

  2. CalMac amends timetables after a 2-week delay to Loch Seaforth

  3. CalMac profit falls as reliability drops

  4. Good Shepherd IV to stay off the Fair Isle run into early November

  5. Colintraive dredging finished as Portavadie closes to vehicles until 16 November

All items in Newbuilds & Orders